A response on behalf of a parents group questioning the more than two-year delay in the start of construction of a new school in Newcastle, has contended that parents are not buying the reasons for the delay put forward by Kawartha Pine Ridge (KPR) District School Board.
“The schedule reflects the combined time required to refine the design, incorporate feedback from families and staff, coordinate with municipal partners through the site plan approval process, and prepare construction drawings and tender documents for a K-12 facility,” KPR Superintendent Vikki Ernst, had explained earlier (see below). KPR already owns the site.
Shifting Timelines
“While I respect that designing a joint K-12 facility requires careful coordination, the current pace remains a serious concern for local families, especially as target timelines keep shifting and extending with every update we receive,” said parent representative Justin Stein in a response made widely available.
Foster Northwest K-12 school in the Municipality of Clarington has long been in planning to serve Newcastle and the surrounding area. Provincial funding of over $75 million was secured in January 2025. Ground breaking has been pushed once again to spring 2027—following previous targets of spring, summer, and fall 2026.
Northglen An Example
“I understand the timeline differs for a private residential project vs a public school; however the benchmarks are easy enough to find online. For example, construction started on Northglen ~2 years after provincial funding was approved,” said the response.
“Even under a conservative timeline for a complex institutional project – allowing ample time for detailed designs, municipal reviews, and engineering specs – standard industry references indicate that a 100 per cent completed construction drawing set and cost evaluation typically take 12 to 18 months. Based on those general benchmarks, the tender package should have been completed between late 2025 and spring 2026. Given where we are today, the project appears to be running well behind even a generous pre-construction schedule, further emphasized by the timeline changes in the last three published updates,” the response said.
Detail The Pre-construction Phase
It pointed out that the core issue for Newcastle families is getting shovels in the ground. “Deferring an updated schedule until after a general contractor is hired leaves the community in the dark about the current pre-construction phase, which is where the delay is actually occurring.”
The response encouraged the board to share a simple breakdown of the remaining pre-construction steps:
- Specifically when the tender package will be finalized,
- The expected public bidding window, and
- The targeted groundbreaking date.
“It would be helpful to know who at the board is responsible for ensuring these items are completed on the new schedule, and if any mitigation steps are in place to avoid any further delays,” the response said.
Earlier Story