Brock Council has endorsed the MacLeod Park Concept Plan timeline, which is currently sitting at 10 years. It did not mention any investment projections.

The MacLeod Park Concept Plan was presented to council last October 14. Staff were directed to establish an internal committee to assist with the proposed development plan.

The park is touted as the recreational heart of Cannington in the Township of brock.

The projects included:

  1. Utility extension for future splash pad, washrooms, and lighting
  2. Multi-purpose sports field
  3. Basketball court
  4. Pickleball courts
  5. Accessible walking paths
  6. Walking trails
  7. Updated pedestrian bridge
  8. Parking lot reduction
  9. Plazas
  10. Entrance signage
  11. Pump track
  12. Dog park
  13. Washroom facilities and water fountain
  14. Baseball diamond lighting
  15. North park improvements (walking paths, tennis courts, benches, planting)
  16. Tree planting
  17. Plaza planting
  18. Pedestrian scale lighting
  19. Splash pad
  20. Parking lot revitalization

Below is a map of some of the coming improvements.

The pedestrian bridge has been restored and parks staff are planning on painting this summer. New signage has been ordered and will be installed upon delivery. The former skateboard area is being transformed into a basketball court and the current single basketball court is being investigated to become a pickleball court.

Due to Source Water Protection restrictions, a large area of MacLeod Park is impacted, including the dog park, which is not able to be developed in this space. Restrictions on fertilizer use may also have impacts on new and existing components of MacLeod Park including the Cannington Lawn Bowling facility.

The top priorities of the members of the internal committee were identified as:

  1. Walking and accessible paths
  2. Washroom building construction
  3. Pump Track

The phases for the park are broken down as follow:

Phase 1, Year 0 to 4
• Utility extension for future splash pad, washrooms and lighting
• Multi-purpose sports field
• Basketball court
• Pickleball courts
• Accessible walking paths
• Walking trails
• Updated pedestrian bridge
• Parking lot reduction
• Plazas (northeast plaza and central entrance plaza)
• Entrance signage at Peace Street and central plaza

Phase 2, Year 4 to 7
• Pump track
• Dog park
• Washroom facilities / water fountain
• Baseball diamond lighting
• North park improvements (walking paths, tennis courts, benches, planting)
• Tree planting
• Plaza planting

Phase 3, Year 7 to 10
• Pedestrian-scale lighting
• Splash pad
• Parking lot revitalization

Below is a map of more planned improvements to MacLeod Park.

You May Also Wish To Read

Plan for three new developments of 1,495 units in Clarington

New 21,000-sqft funeral centre at Duffin Meadows Cemetery

Tributes pour in for community builder Gord Lowery

New upgrades added during Sunderland Arena works

Deputy chief who used slur, reported own speeding, out of job

Leave a Reply