New upgrades added during Sunderland Arena works

The Township of Brock has announced that throughout renovation, several important enhancements have been incorporated into the $10.2 million Sunderland Memorial Arena Renovation Project.

With the major structural, servicing, and building upgrades underway, and provided no additional unforeseen conditions arise, substantial completion of this project is currently anticipated by the end of October.

The project continues to make excellent progress, the township said  adding that as one of the largest capital projects undertaken in many years, this redevelopment was always anticipated to be a complex undertaking, with an expected construction timeline of about 12 to 18 months.

“While early schedules reflected the shorter end of that range, the realities of renovating a facility originally built in 1977 have presented opportunities to address several unforeseen conditions and improve the building beyond the original scope. Much like any major renovation of an older building, once walls and systems are opened up, unique challenges and opportunities for long-term improvements are often uncovered,” said the township.

Front lobby

Several of the incorporated enhancements include:

  • Relocation of an existing hydro pole and reconnection of services to facilitate construction of the new dressing room addition.
  • Construction of a new pre-engineered steel extension connecting seamlessly to the existing facility.
  • Installation of additional structural steel beams and columns to support the second-floor kitchen and washrooms following modifications to the main floor layout and creation of new washroom facilities.
  • Upgrades to the sewage system and other existing underground infrastructure to improve long-term reliability.
  • Enhancements to the watermain connection, improving both fire protection capabilities and domestic water supply throughout the facility.
Entrance to lobby

While the construction site is closed to the public, the township has also taken advantage of the opportunity to accelerate several facility improvements that had originally been slated for 2028-2029 capital projects. By completing this work now, the township will avoid future disruptions to arena operations and user groups, it said.

These additional improvements include:

  • A new roof over the new ice surface
  • A new rooftop HVAC system
  • A new efficient furnace unit
Ice Plant Training

Following construction, several critical steps must still occur, and staff have allocated 4-5 weeks in November to train staff on the new ice plant equipment, install ice and complete any remaining finishing touches.

At this time ice allocation for local user groups is expected to commence on December 7th.

The Sunderland Lions and township are currently working on opening celebrations, prior to ice usage, and information on the date and event details will be coming out shortly, the township said.

Project highlights and pictures of construction updates can always be found here.

Earlier Story

$10.2mn Sunderland Arena project finally gets underway

You May Also Like To Read

Deputy chief who used slur, reported own speeding, out of job

Man tried to scissor off handbag from senior shopper

Man drove through playground, splash pad, paths with people

Carjacker with cocaine draws police with dangerous driving

Edgerton Bridge closed for replacement until mid-December

Leave a Reply