Durham Region has scheduled construction for the third segment of the Durham-Scarborough Bus Rapid Transit (DSBRT) from today Monday, September 28, until August 31, 2028.
It, of course, mentioned unfavourable weather conditions may impact the work schedule.
The works will take place in the City of Pickering along Kingston Road (Regional Highway 2) from Steeple Hill to Merritton Road.
The Regional Municipality of Durham has retained Limen Construction Ltd. to undertake the proposed works, which will include the following:
• Reconstruction of the existing pavement along with dedicated median bus lanes.
• Construction of new median transit stop platforms and stations.
• Installation of new water supply systems.
• Accessibility improvements to existing sidewalks.
• Construction of a new wastewater system utilizing microtunnelling methods.
• Installation of new traffic signals with dedicated bus movements.
• Construction of new in-boulevard cycle tracks.
• Improvements to roadway and boulevard lighting.
• Additional landscaping, including new trees and plantings along the corridor.
“Limen Construction Ltd. will mobilize on site beginning September 28, 2026, to commence preparatory activities for the project. Construction is anticipated to be completed by August 31, 2028, subject to weather conditions and construction progress. Public notices and further information will be posted to this website as updates become available,” said a region notice.
The value of the contract was not mentioned.
Lane Shifts & Restrictions
The region said lane shifts and restrictions will be in place throughout construction.
From late October this year to summer 2027, Kingston Road will be reduced to one eastbound lane and two westbound lanes for an extended period to accommodate major wastewater construction.
In late 2027, Kingston Road will be reduced to one lane in each direction at the intersections of Whites Road and at Fairport Road for longer durations to facilitate construction of the new transit stop platforms.
Bus routes, bus stops, sidewalks and businesses will remain open for the duration of construction.
The region said it realizes that the work may be disruptive and will make every effort to complete the work as quickly and efficiently as possible. Drivers are asked to exercise caution for the safety of pedestrians, cyclists and work crews.

This project is partially funded through the Investing in Canada Infrastructure Program (ICIP).
The DSBRT will feature 36 kilometres of dedicated bus lanes, delivering faster, more reliable service through Oshawa, Whitby, Ajax, Pickering and Scarborough along Highway 2.